Village Hall Build Blog
RSS
Curtains
3/15/2015 10:34:47 AM
 
Blinds & curtains finish off the decor.
Practical Completion Meeting
3/15/2015 10:30:41 AM

All signed off at the Pratical Completion Meeting with Geoff Slater from the BIG Lottery.
Finished - almost!
1/11/2015 9:58:53 AM
     
     
 
 A tour of the finished building - now on to the landscaping!
Dec 18th - Handover!
1/11/2015 9:46:20 AM
 
The committee and contractors celebrate completion of the build - on time and within the budget!
Dec 14th - Nearly done!
12/14/2014 7:33:37 PM
       

Nov 30th - Painting
11/30/2014 4:57:06 PM
  
The decorators are in and the main hall lighting has arrived at last.
Nov 20th - Up on the Roof!
11/20/2014 10:04:14 PM
  
Up on the roof admiring the view. Tiling, plastering and woodwork coming on well. 
Nov 11th - Plastering
11/11/2014 6:49:12 AM
 
Plastering has started and tiling of the front elevation with the original tiles.
Nov 1st - Windows
11/1/2014 9:10:46 PM
  
Banishing the cold drafts with double glazed windows and roof insulation. One half of the extension roof is now tiled.
Oct 25th - Ready for Tiling
10/26/2014 1:34:22 PM
  
Work has started on putting the roof back on.
Oct 24th _ Date Stone
10/26/2014 1:24:39 PM
 
Thanks to Richard for carving a date stone for the extension.
 
Oct 15th - New Roof
10/15/2014 4:04:37 PM
 
The exisiting trusses have been reinforced and work on the kitchen roof started. On the extension, the first truss has be added.
Sep 29th - Walls!
9/29/2014 8:25:58 PM
   
The building is taking shape as the walls go up.
Sep 23rd - The new floor
9/24/2014 9:17:30 PM
   
The new floor goes in - no more weeds through the floor boards!
Sep 17th - E&M site meeting
9/18/2014 7:46:12 AM
 
Site meeting to finalise the electrics and plumbing - indoor toilets at last!
Sep 9th - Ready for the concrete
9/9/2014 9:51:15 PM
 
The extension excavations are complete, ready for the concrete to be poured in tomorrow and the rebuilt brick pillars are nearly finished.
Sep 3rd - A peek inside
9/3/2014 10:03:02 PM
 
A quick look at what is going on inside the building.
Sep 2nd - Trenches
9/2/2014 2:50:09 PM
Work starts on digging out trenches for the new water supply and drains.
Aug 29th - Lowering the floor
8/29/2014 7:24:24 PM
          
Removal of the compacted earth under the floor requires skillful digging. New internal wall is finished.
Aug 18th - Hole in the wall
8/18/2014 9:01:33 PM

Work begins on taking down the back wall.
25 items total 1  2 
August, 2014
September, 2014
October, 2014
November, 2014
December, 2014
January, 2015
March, 2015
HomeAbout HeathEvents & ActivitiesLocal FacilitiesWell dressingsPicture GalleryHiring the Village HallContacts & Useful LinksVillage Hall Build Blog